A) draw a network for the situation
B) Identift the critical path for this project
c) What is the minumum time that the project can be completed in?
Math question urgent, c website for table?
i will help in letter (c)
t = 0 : Amy......... .......... Bob ........... .......... Cam
(clean kitchen) ........ (clean window) ...... (mow lawn)
t = 30 .... Bob finishes (B), starts vacuuming
t = 50 .... Bob finishes (C) ... waits for others
t = 60 .... Amy finishes (A), starts with carpet
............... Bob still waits for the last work
............... Cam finishes (D), starts trimming hedges
t = 90 .... Amy finishes (F) ... ends work.
t = 120 .. Cam finishes (E) , ends work.
............... Bob takes rubbish
t = 150 .. Bob ends...
so it takes them 150 minutes at least...
§